FCC clears SpaceX to build a million-satellite orbital data center
The FCC authorized SpaceX to deploy up to 1 million Starmind satellites as orbital data centers, the first US approval of its kind. One satellite must fly by 2033 and the full constellation by 2040.
What happened
The US Federal Communications Commission approved SpaceX on November 25 to deploy up to one million low-orbit satellites that would run data centers in space. The order is DA-26-1273 and the constellation is called Starmind. The FCC described it as the first US authorization for an orbital data center constellation.
The approval came as a market access and authorization grant, signed by Space Bureau chief Courtney Reinhard, under application SAT-LOA-20260108-00016.
What the license covers
The satellites sit between 500 and 1,002 kilometers, in shells spaced 50 kilometers apart, at 30-degree and sun-synchronous inclinations. The main link is optical inter-satellite communication, with connections into the Starlink Gen1 and Gen2 networks.
Ka-band is a backup only: 18.8 to 19.3 GHz downlink and 28.6 to 29.1 GHz uplink, for emergency telemetry and commands. SpaceX said it does not plan to run Starmind in Ka-band except for limited emergency operations.
Several conditions matter. Debris plans below 600 kilometers were found compliant. Above that altitude the re-entry waiver was deferred, so SpaceX must file again before deploying there. The surety bond requirement was waived. The license runs 15 years from certification of the first working satellite, with semiannual reports on interference, deorbits and satellites in orbit.
The milestones are the real schedule
One million is a ceiling, not a plan. The order sets these dates: one satellite in orbit and operating by November 25, 2033, then 10 percent by 2035, 50 percent by 2038, and the full constellation by 2040.
At that pace there is exactly one Starmind satellite in space before 2033. Reading the ceiling as capacity misreads the document.
Elon Musk said at the Baron Investment Conference this month that the first Starmind computers could launch in the third quarter of 2027. He called that date a guess. SpaceX is also working with Nvidia on hardware for orbital AI computing.
Where to discount
Solar power and vacuum cooling are the pitch, but the engineering constraints remain. Each satellite is limited by solar array area, radiator area and structural mass. Inter-satellite links and ground downlinks both have bandwidth ceilings.
A preprint released on November 22, not yet peer reviewed, estimated that launches and re-entries at million-satellite scale could push emissions above 150 times the 2025 level. Treat that figure with care. It does explain why the disposal rules above 600 kilometers were put on hold.
The decisive variable is cost per watt. Terrestrial data centers are limited by power and grid queues. Orbital ones are limited by launch and maintenance. Capital will follow whichever falls first.
What to watch
Three markers. First, the launch date of the first Starmind satellite and the Nvidia payload specs. Second, when SpaceX files for orbits above 600 kilometers. Third, how the FCC handles applications from other companies.
Nothing here is investment advice.
Source: FCC