Drax prices powered land for AI campuses at $1M per megawatt
Drax will build a GW-scale AI data center in three phases with Brookfield and Radiant, pricing powered land at about $1M per megawatt. No tenant is signed.
Two announcements at one capital markets day
On November 23, UK generator Drax delivered two things at once: higher earnings guidance, and a partnership to build an AI data center on its own power station site.
The company said 2026 adjusted EBITDA will come in well above the analyst consensus of £721 million, which sat in a range of £710 to £736 million as of November 17. Strong system support and generation in September and October, plus balancing mechanism income, added about £50 million to its 2026 contracted power position.
The shares rose roughly 5.4% to 6.1% to 866–872 pence, against a previous close of 821.5p. The 52-week high was 937.5p in February.
Three phases on the station estate
The partners are Brookfield and Radiant, Brookfield's UK-headquartered AI infrastructure platform. Investment capital and operating capability come through a Brookfield-Qai AI infrastructure joint venture. The project sits on the 1,000-acre Drax Power Station estate and runs in three phases, with the potential for GW-scale capacity in total.
One number matters most. The agreement provisionally values powered land across all three phases at about $1 million per megawatt. Drax is not selling electricity here. It is selling a position that already holds a grid connection and can start building.
Read the timeline with care. Radiant has spent 2026 discussing commercial terms with potential tenants for phase one, and those talks are ongoing. No tenant has signed. Phase one also needs planning approval, government and network regulatory approval, an acceptable tenant, negotiated commercial agreements and a final investment decision from each party.
Drax has separately requested 1.2GW of import capacity from the system operator. It is also studying non-generation stability services, such as inertia, from two units that do not currently run, with work continuing through 2027.
From biomass to energy plus real estate
The mid-term targets describe a change in mix. Adjusted EBITDA is targeted at £800 to £900 million in 2029 and above £1 billion by 2031. The 2029 midpoint of £850 million is about 18% above the 2026 consensus, implying average growth above 12% a year from 2027 to 2031.
Dividend per share is targeted to grow more than 10% a year. Drax also plans about £800 million of shareholder returns from 2026 to 2031, with more than £3 billion of free cash flow over the same period. The net debt to EBITDA target rises from about 2x to 2.5x. The buyback stays paused.
The funding is disclosed too: a completed £300 million term loan and a €1 billion euro bond, extending maturities to 2032.
One line in the mix deserves a note. Biomass generation produced more than 80% of 2025 EBITDA. By 2029 the company expects solar, wind and flexible generation, meaning batteries and gas peakers, to be the majority. Three newly approved UK solar projects are worth about £120 million.
Why the market pays before a tenant signs
The logic is that scarcity has moved. For a decade data centers competed on chips and power prices. Now they compete for land that already has interconnection capacity. Grid queues in the UK run for years, so an estate with a live connection, 1,000 acres and its own generation is a permit in itself.
For Drax, the accounting effect matters more than near-term cash. Once a first lease validates the $1 million per megawatt figure, the estate stops being an appendage of a generation asset. It becomes land that can be priced, mortgaged and sold to infrastructure funds. Brookfield brings capital, Qai brings operations, and Drax brings the land and the power.
Five risks
First, there is no tenant. Phase one terms are still under discussion, and if they fail the valuation is only a paper figure.
Second, the approval chain is long. Planning, government and network operator gates can each delay the schedule.
Third, the valuation is provisional, not a transaction price.
Fourth, raising the leverage target from 2x to 2.5x means funding growth from the balance sheet, which raises rating sensitivity.
Fifth, biomass cash flow is declining. After the ROC scheme ends in March 2027, replacement revenue depends on new low-carbon dispatchable contracts and flexible assets, and execution risk sits there.
What to watch
The first phase-one lease, and whether its actual rate holds near $1 million per megawatt. Once that number is public, the powered land at other old UK stations, including closed coal plants, will be repriced.
Nothing here is investment advice.
Source: Drax Group